• <noscript id="y4y0w"><source id="y4y0w"></source></noscript>
    <table id="y4y0w"><option id="y4y0w"></option></table>
  • <li id="y4y0w"></li>
    <noscript id="y4y0w"></noscript>
    <noscript id="y4y0w"><kbd id="y4y0w"></kbd></noscript>
    <noscript id="y4y0w"><source id="y4y0w"></source></noscript>
    <menu id="y4y0w"></menu>
    <table id="y4y0w"><rt id="y4y0w"></rt></table>
  • 考慮非線性蠕變的露天礦邊坡預警閾值確定

    Determination of early warning threshold for open-pit slope considering nonlinear creep

    • 摘要: 露天礦邊坡監測作為保障人員與設備安全的最后一道防線,其核心在于構建精準的預警閾值. 當前我國露天礦邊坡監測系統存在預警閾值設定缺乏系統性和閾值確定缺乏科學理論支撐的問題. 對此,本研究提出基于蠕變理論的預警方法:圍繞蠕變曲線發展規律與累計位移量變化特征,通過解析邊坡蠕變三階段的臨界位移比例關系來確定預警值. 基于礦區代表性巖石力學參數,通過PFC3D離散元模擬構建簡化巖體模型,進行常三軸壓縮試驗獲取應力–應變曲線,反演得到用于蠕變方程的本構參數(彈性模量和黏度系數),再建立蠕變方程推導出位移比例關系式. 基于模擬的蠕變曲線得出方程所需的關鍵點及三級蠕變的起點值,并引入鎖固段破壞機制概念和重正化群理論量化空間變異影響,推導臨界位移閾值,進而求出蠕變演化的四級預警值,并與露天礦C現場GNSS監測的累計位移數據進行對比,驗證預警閾值的準確性. 對于突發的異常變形,引入切線角判據完善預警機制. 試驗表明,以露天礦C預警閾值為例,蠕變發出Ⅰ級預警(6216 mm)至滑坡發生提前了11.6天,之后進行短期的變形速率預警閾值監測,當變形速率發出Ⅰ級預警(97.2 mm·d?1)后3小時發生滑坡. 通過長短周期預警的協同作用,提升了預警系統的準確性和可靠性.

       

      Abstract: Stability monitoring of the open-pit slope is the last key line of defense for ensuring the safety of mine personnel and integrity of production equipment. Setting scientific, accurate, and reliable early warning thresholds can enhance monitoring effectiveness. However, the current open-pit slope monitoring system in China is lacking in scientific theoretical support and methodology in setting early warning thresholds. To address this problem, this study proposes an innovative method for constructing early warning thresholds based on slope creep theory. The core idea of this method is to deeply explore the internal development law of the slope creep curve, especially the evolution characteristics of cumulative displacement with time. The research focuses on the three classic stages of the slope creep process (initial, steady state, and accelerated). The displacement ratio, determined by an analysis of the critical point between the three stages, can be used as a key scientific basis in determining and grading warning thresholds. First, the representative rock mass mechanical parameters of the target open-pit mine C were selected, and a simplified rock mass model, which can reflect the key structural characteristics, was constructed using three-dimensional (3D) particle flow code (PFC) discrete element numerical simulation software. The stress–strain curves of rock mass under different stress levels were obtained via a numerical simulation of a conventional triaxial compression test. Based on the simulated stress–strain curves and creep theory, the key parameters of the constitutive equation describing the creep behavior of rock mass—namely, the elastic modulus and viscosity coefficient—were determined. Additionally, the concept of the locking segment failure mechanism was introduced, and renormalization group theory was applied to quantify the influence of the spatial variability of rock mass on macro strength and deformation. The creep proportional relationship was combined with locked segment theory and the quantitative results of spatial variability to derive a critical displacement threshold, which is more in line with the actual geological conditions. Based on the evolution characteristics of the critical displacement threshold and creep curve, thresholds for a four-level early warning system were determined to provide a hierarchical response basis for different stages of deformation. To verify the accuracy and practicability of the proposed method, the derived early warning thresholds were compared with the long-term cumulative displacement data obtained by the mine site monitoring global navigation satellite system (GNSS). The results show that the threshold constructed based on creep theory can effectively capture the key deformation stage before slope instability. Taking open-pit mine C as an example, the creep theory early warning based on cumulative displacement sent an alarm when the Level I early warning threshold (6216 mm) was reached, 11.6 days ahead of the final landslide occurrence time, providing a valuable time window for emergency response and personnel and equipment evacuation. At the short-term acceleration stage near the landslide, the landslide occurred only 3 h after the Level I warning threshold (97.2 mm) triggered by the deformation rate (tangent angle criterion), capturing the rapid acceleration process before the final instability. The accuracy and reliability of the early warning system were improved through the synergy of long- and short-term early warning mechanisms.

       

    /

    返回文章
    返回
  • <noscript id="y4y0w"><source id="y4y0w"></source></noscript>
    <table id="y4y0w"><option id="y4y0w"></option></table>
  • <li id="y4y0w"></li>
    <noscript id="y4y0w"></noscript>
    <noscript id="y4y0w"><kbd id="y4y0w"></kbd></noscript>
    <noscript id="y4y0w"><source id="y4y0w"></source></noscript>
    <menu id="y4y0w"></menu>
    <table id="y4y0w"><rt id="y4y0w"></rt></table>
  • 啪啪啪视频